Independent infrastructure intelligence

Track the power behind AI data centers.

Permits, turbines, power transitions, and community claims—organized into timelines you can verify.

First tracker verified Aug 11, 2026

Featured tracker

One promise.
Twelve months.

SpaceXAI says all 69 temporary turbines at its Southaven facility will be removed as a permitted permanent power plant comes online. This tracker separates the schedule from independently verified progress.

Removal scheduled 69 units scheduled to leave.

The company says removal will start as early as August 2026 and finish by July 2027.

69 0
Removed count not independently verified
Earliest start Aug 2026
Committed deadline Jul 2027

The verified numbers

Temporary turbines 69

Company-reported fleet scheduled for removal

Verify source ↗

What changed

The record,
not the cycle.

We turn announcements, permits, reporting, and public testimony into a dated project history. Each update stays connected to the source that supports it.

How it works

Evidence before velocity.

The product is intentionally small. We do not publish a number because it looks plausible; we publish it when a reader can follow it back to a record.

01

Collect primary records

Company updates, permits, regulator pages, filings, and court records form the base layer.

02

Separate claims from facts

Company statements, outside reporting, and community concerns retain their source and speaker.

03

Publish the change

Material changes appear in a dated timeline with a last-verified stamp and correction path.

Built for verification

Three readers.
One record.

Public project information should stay public. The same record can serve a deadline-driven reporter, an infrastructure analyst, and a neighbor living with the project.

Journalists

Get the current status fast.

Find the number, date, and primary link without reopening a month of tabs.

Researchers

Keep the provenance intact.

Trace project claims through permits, reporting, and versioned updates.

Communities

See what was promised.

Compare public commitments with the project timeline in plain English.

Source standards

Not all links carry equal weight.

Our labels tell you whether you are reading a primary record, a company statement, established reporting, or a documented community concern.

Primary

Regulatory records

Permits, filings, official orders, and court documents.

Attributed

Company statements

Useful for commitments and plans, always labeled as the company’s position.

Context

Independent reporting

Reputable local, national, trade, and investigative coverage.

Questions, answered

Is this an official SpaceXAI tracker?

No. Compute Grid Watch is independent and is not affiliated with SpaceX, xAI, SpaceXAI, or any regulator. We link directly to their records where relevant.

Is the removal count real-time?

No. The site tracks verified disclosures and explicitly marks the current removed-unit count as unverified. We do not infer physical progress from the calendar.

Where do 69, 41, and 1.2 GW come from?

The 69-unit removal plan and 1.2 GW replacement come from the company’s July 30 update. The 41 permanent turbines also appear in state permit records cited by reporting. Every metric links to its source.

Does “unpermitted” mean illegal?

We do not make that legal conclusion. We attribute the term to reporting, litigation, or regulators and preserve the source’s wording and context.

How are corrections handled?

Material corrections are added to the project update log with the date, what changed, and the supporting source. See our methodology for the full rule.